Tag Archives: DPU

More Detail on the Massachusetts DG Interconnection Docket

On Monday, August 19, the Massachusetts Department of Public Utilities (“DPU”) provided additional information on the timing, process, and scope of its investigation into DG interconnection.  The full memorandum from the Hearing Officer is here.  This procedural update follows the July 18 technical conference, which we summarized here.  A few key points from the memorandum:

  • Three additional technical conferences have been scheduled in the docket for October 3,…
  • More

Massachusetts DPU Opens Docket on DG Interconnection

On May 22, 2019, the Massachusetts Department of Public Utilities (“DPU”) opened a new docket (D.P.U. 19-55) to investigate the interconnection of distributed generation (“DG”) in Massachusetts.  (And yes, the DPU intends to include energy storage interconnection in this docket despite defining DG as “technologies that generate electricity”.)

While complaints about costs, delays, and increased volume of interconnection applications have been growing,… More

Massachusetts DPU Issues Decisions on Energy Storage and Capacity Rights

On February 1, 2019, the Massachusetts Department of Public Utilities issued two long-awaited orders in docket D.P.U. 17-146. The orders address a number of issues related to pairing energy storage systems (“ESS”) with net metering facilities and the rights to the capacity associated with net metering and SMART facilities. There are too many issues in these orders to address each fully here, but below are some high-level highlights.… More

SMART is Open!

November 26th was a big day for solar energy in Massachusetts.  As promised, the Massachusetts Department of Energy Resources (“DOER”) opened the application portal for the long-anticipated SMART Program.  Applications received between November 26th and November 30th will be considered to have been received at the same time.  Starting on December 1st, applications will be reviewed on a first come, first served, basis.

Also on November 26th,… More

National Grid Seeks $166 Million for Electric Vehicle Infrastructure Development Program

As part of its petition seeking an increase in distribution rates and approval of a performance-based ratemaking plan, which was filed with the Massachusetts Department of Public Utilities (DPU) on November 15, 2018, National Grid is requesting up to $166.5 million to implement Phase II of its Electric Vehicle Market Development Program. In September, the DPU approved Phase I of National Grid’s EV Program—which provides over $20 million for,… More

MA DPU Approves Significant Investments and Upgrades to State’s Grid Modernization Technologies

On May 10, 2018, the Department of Public Utilities (DPU) issued an Order approving significant grid-facing investments and upgrades to the state’s electric grid. Specifically, the DPU’s Order authorizes Massachusetts’ utility companies to make $220 million in grid-facing investments in grid modernization technologies over the next three years to upgrade their distribution systems to improve the efficiency and reliability of the electric grid. In the Order, the DPU noted that the Order establishes the platform and the method for the electric distribution companies to make initial investments in grid modernization technologies to upgrade their current infrastructure and to increase the use of renewable energy,… More

TUE Committee to Hold Hearing on DPU’s Approval of MMRC Demand Charge

Massachusetts Legislators are taking a look at the Department of Public Utilities’ (DPU) recent approval of an Eversource Energy proposal to apply different rate structures to customers who participate in net metering, such as customers who install solar energy systems at their homes or businesses.  The Joint Committee on Telecommunications, Utilities and Energy (TUE) will hold an oversight hearing on the DPU’s recent decision in the Eversource Energy rate case to approve Eversource’s proposal to include a demand charge as a part of a monthly minimum reliability contribution (MMRC) applicable to net metering customers.  … More

DOER Releases Results of SMART Procurement

This afternoon, the Massachusetts Department of Energy Resources (DOER) released the much-anticipated results of the competitive procurement that will set the base compensation rates for the SMART program.  The base compensation rates range from $0.17 in the NSTAR and Nantucket Electric territories to about $0.14 in WMECO.  In Massachusetts Electric territory, the non-Nantucket territory served under the National Grid umbrella, the base compensation rate is about $0.16.  A DOER summary table of the procurement is below. … More

Massachusetts Department of Public Utilities Investigates Issues Relating to Net Metering, Energy Storage, and Forward Capacity Market Participation

On October 3, 2017, the Massachusetts Department of Public Utilities (“DPU”) opened a new docket (D.P.U. 17-146) to investigate two issues: whether energy storage systems paired with net metering facilities are eligible for net metering and what should be done to clarify the rights of net metering facilities to participate in the Forward Capacity Market (“FCM”).

These issues have been percolating for years.  In fact, D.P.U.… More

SMART Moves to a New Forum: Massachusetts Department of Public Utilities to Consider a SMART Tariff

Stakeholders have been following the development of “SMART” as a successor to the SREC program in Massachusetts for more than a year.  (See our previous posts on the development process here, here, and here.)  As it stands, SMART reflects a determined effort by the Department of Energy Resources (“DOER”) to craft a program that balances multiple interests and sets a sustainable path for solar development in Massachusetts. … More